A Practical Way to Schedule Irrigation From Soil Water
The soil is a reservoir, and irrigation is how you refill it before the crop runs dry. The trick is knowing how big the reservoir is, how fast it drains and when to top it up. That is all scheduling really is, and it does not require anything fancier than a notebook, a rain gauge and a soil probe.
Step one: know your reservoir
Water available to the crop sits between field capacity, the upper limit after drainage, and the permanent wilting point. University of Minnesota Extension multiplies rooting depth by available water-holding capacity per inch of soil to get the total. Finer soils hold more than sands. The USDA Web Soil Survey will tell you what soil you have. Rooting depth matters too, and Minnesota lists about 36 inches for corn, 24 inches for soybean and 48 inches for alfalfa. Annual crops often take 30 to 50 days to reach full depth, so do not credit the whole profile early.
Step two: set the trigger
Management allowed depletion, or MAD, is the share of available water the crop may use between irrigations. The old standard was 50 percent, but Minnesota says it can be adjusted by crop, growth stage and soil. NDSU's version has corn and soybean going to 60 percent during vegetative growth and staying at 50 percent or less at flowering. For corn, Minnesota's table calls for 40 to 50 percent from about V12 to pollination, so that is when to keep the reservoir fuller.
Step three: keep the books
NDSU's checkbook method treats rain and irrigation as deposits and crop water use as withdrawals:
- At emergence, estimate the starting deficit by feeling soil in 6-inch layers through the root zone.
- Each day, add that day's crop water use to the running deficit. Use ET figures from tables or a local weather service.
- Subtract rain, measured with at least one and preferably two gauges in or near the field, and any irrigation applied.
- If the number drops below zero, enter zero. The soil is full.
- Irrigate when the deficit reaches your allowed depletion, and apply no more than the current deficit so water is not lost to leaching.
Step four: look ahead and check the books
A center pivot can take days to cover a field, so schedule a few days ahead and look at the forecast. Leave room for rain. Every couple of weeks, probe the soil in several places, and replace the calculated deficit with the measured one if they disagree. Sensors can help too, but they work best as a check on the bookkeeping.
Keeping it manageable
Minnesota estimates upkeep at about 5 to 20 minutes a day once the soil work is done, with soil moisture checked at least twice a week. Keep a balance sheet per field with date, high temperature, crop use, rain, irrigation and deficit. If your time is short, a crop consultant can run it for you. For details and ET tables, see the NDSU checkbook method publication and Minnesota's irrigation scheduling basics.